Dept. of Trans. PROGRESS Serial No. Contract No. 11-144-08-35 06-324504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 1% 6% 06-TUL-99-41.3/53.9 Federal Project: 06-FRE-99-0.0/1.2 HPLU-6206(10) L-6206(10) Progress payment No. 03 Payment period ending: 05-20-11 DIABLO CONTRACTORS INC 7 CROW CANYON COURT SUITE 100 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 600,876.58 387,038.28 2.a. Extra Work 24,291.99 18,137.64 b. Adjustment Comp. 3. Materials on Hand 219,802.00 15,674.23 4. Earned Subject to Retention 844,970.57 420,850.15 5. Mobilization 6. Total Work Completed 625,168.57 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 844,970.57 420,850.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 420,850.15