Dept. of Trans. PROGRESS Serial No. Contract No. 15-111-13-18 06-324504 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 98% Location: Federal Project: 06-TUL-99-41.3/53.9 HPLU-6206(10) 06-FRE-99-0.0/1.2 L-6206(10) Progress payment No. 052 Payment period ending: 04-20-15 DIABLO CONTRACTORS INC 7 CROW CANYON COURT SUITE 100 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 59,358,129.18 60,923.04 2. a. Extra Work 3,017,185.12 376,222.87 b. Adustment Comp. 2,504,918.30 0.00 3. Materials on Hand 280,860.75 0.00 4. Earned Subject to Retention 65,161,093.35 437,145.91 5. Mobilization 6,200,000.00 0.00 6. Total Work Completed 71,080,232.60 7. Deductions -206,217.64 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 71,154,875.71 437,145.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 437,145.91