Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-256-14-42 06-324504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-TUL-99-41.3/53.9 HPLU-6206(10) 06-FRE-99-0.0/1.2 L-6206(10) Progress payment No. 060 Payment period ending: 10-30-15 DIABLO CONTRACTORS INC 7 CROW CANYON CT #100 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 62,530,638.37 0.00 2. a. Extra Work 3,779,333.73 0.00 b. Adustment Comp. 1,741,099.39 -210,978.96 3. Materials on Hand 4. Earned Subject to Retention 68,051,071.49 -210,978.96 5. Mobilization 6,200,000.00 0.00 6. Total Work Completed 74,251,071.49 7. Deductions -1,752,723.04 210,978.96 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 72,498,348.45 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00