Dept. of Trans. PROGRESS Serial No. Contract No. 13-056-14-08 06-324514 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 6% 06-TUL-99-R48.5/R53.9 Federal Project: 06-FRE-99-R0.0/R2.6 NONE Progress payment No. 02 Payment period ending: 02-20-13 W A B O LANDSCAPE & CONSTRUCTION INC 726 ALFRED NOBEL DRIVE HERCULES CA 94547 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 146,385.69 123,710.69 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 28,302.00 28,302.00 4. Earned Subject to Retention 174,687.69 152,012.69 5. Mobilization 158,500.00 158,500.00 6. Total Work Completed 304,885.69 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 333,187.69 310,512.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 310,512.69