Dept. of Trans. PROGRESS Serial No. Contract No. 14-325-08-55 06-324514 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 06-TUL-99-R48.5/R53.9 Federal Project: 06-FRE-99-R0.0/R2.6 NONE Progress payment No. 23 Payment period ending: 11-20-14 W A B O LANDSCAPE & CONSTRUCTION INC 726 ALFRED NOBEL DRIVE HERCULES CA 94547 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,632,148.66 7,405.71 2.a. Extra Work 45,030.77 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,677,179.43 7,405.71 5. Mobilization 317,000.00 0.00 6. Total Work Completed 1,994,179.43 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,994,179.43 7,405.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,405.71