Dept. of Trans. PROGRESS Serial No. Contract No. 15-113-14-25 06-325514 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 18% Location: Federal Project: 06-KIN-198-8.9/10.1 NHP-P198(64) Progress payment No. 001 Payment period ending: 04-20-15 WABO LANDSCAPE & CONSTRUCTION, INC. 726 ALFRED NOBEL DRIVE HERCULES CA 94547 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 237,920.60 237,920.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 237,920.60 237,920.60 5. Mobilization 63,365.00 63,365.00 6. Total Work Completed 301,285.60 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 301,285.60 301,285.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 301,285.60