Dept. of Trans. FINAL Serial No. Contract No. 06-324-09-53 06-327004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-MAD-41-6.8/6.9 Federal Project: NONE Progress payment No. 05 Payment period ending: 07-31-06 AGEE CONSTRUCTION CORPORATION P O BOX 629 CLOVIS CA 93613 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 337,564.13 38,070.00 2.a. Extra Work 3,812.59 3,812.59 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 341,376.72 41,882.59 5. Mobilization 6. Total Work Completed 341,376.72 7. Deductions 0.00 1,000.00 8. a.Contract Retentions -12,230.03 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 12,230.03 0.00 9. Total pay to Contractor 341,376.72 42,882.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,882.59