Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 02-059-09-08 06-338204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-46-20.5/32.5 Federal Project: ACNH-P046(29) Progress payment No. 21 Payment period ending: 02-14-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01538 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,069,626.36 1,500.00 2.a. Extra Work 1,078,418.88 125,374.84 b. Adjustment Comp. 294,687.82 0.00 3. Materials on Hand 4. Earned Subject to Retention 8,442,733.06 126,874.84 5. Mobilization 805,975.00 0.00 6. Total Work Completed 9,248,708.06 7. Deductions -21,000.00 -11,000.00 8. a.Contract Retentions -415,792.91 0.00 b. Unsatisfactory Prog. 0.00 12,153.81 c. Reduction after 95% Comp. 415,792.91 415,792.91 9. Total pay to Contractor 9,227,708.06 543,821.56 10. Reduction Amt to Escrow -415,790.00 -415,790.00 11. Payment to Escrow 415,790.00 12. Net Pymt. this Estimate 128,031.56