Dept. of Trans. PROGRESS Serial No. Contract No. 02-142-13-28 06-342324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 29% 06-FRE-180-R55.4/R56.6 Federal Project: ACNH-X019(15) HP21-6086(10) L-6086(10) Progress payment No. 07 Payment period ending: 05-20-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01856 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,717,855.75 1,427,960.14 2.a. Extra Work 20,910.85 601.22 b. Adjustment Comp. 3. Materials on Hand 193,940.66 -4,160.32 4. Earned Subject to Retention 8,932,707.26 1,424,401.04 5. Mobilization 2,482,431.70 0.00 6. Total Work Completed 11,221,198.30 7. Deductions -55,000.00 0.00 8. a.Contract Retentions -484,204.21 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,875,934.75 1,424,401.04 10. Reduction Amt to Escrow 11. Payment to Escrow 484,200.00 12. Net Pymt. this Estimate 1,424,401.04