Dept. of Trans. PROGRESS Serial No. Contract No. 03-055-10-13 06-342324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 66% 06-FRE-180-R55.4/R56.6 Federal Project: ACNH-X019(15) HP21-6086(10) L-6086(10) Progress payment No. 17 Payment period ending: 02-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01856 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,038,994.56 254,650.57 2.a. Extra Work 355,895.60 3,992.95 b. Adjustment Comp. -14,156.28 -17,306.28 3. Materials on Hand 85,380.77 -34,030.29 4. Earned Subject to Retention 17,466,114.65 207,306.95 5. Mobilization 2,613,086.00 0.00 6. Total Work Completed 19,993,819.88 7. Deductions -62,809.48 0.00 8. a.Contract Retentions -873,305.73 -10,365.34 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,143,085.44 196,941.61 10. Reduction Amt to Escrow 11. Payment to Escrow 500,000.00 12. Net Pymt. this Estimate 196,941.61