Dept. of Trans. PROGRESS Serial No. Contract No. 03-080-10-54 06-342324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 69% 06-FRE-180-R55.4/R56.6 Federal Project: ACNH-X019(15) HP21-6086(10) L-6086(10) Progress payment No. 18 Payment period ending: 03-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01856 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,525,659.21 486,664.65 2.a. Extra Work 378,880.97 22,985.37 b. Adjustment Comp. -9,876.28 4,280.00 3. Materials on Hand 7,513.97 -77,866.80 4. Earned Subject to Retention 17,902,177.87 436,063.22 5. Mobilization 2,613,086.00 0.00 6. Total Work Completed 20,507,749.90 7. Deductions -62,809.48 0.00 8. a.Contract Retentions -895,108.89 -21,803.16 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,557,345.50 414,260.06 10. Reduction Amt to Escrow 11. Payment to Escrow 500,000.00 12. Net Pymt. this Estimate 414,260.06