Dept. of Trans. PROGRESS Serial No. Contract No. 03-112-08-10 06-342324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 73% 06-FRE-180-R55.4/R56.6 Federal Project: ACNH-X019(15) HP21-6086(10) L-6086(10) Progress payment No. 19 Payment period ending: 04-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01856 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,842,942.41 317,283.20 2.a. Extra Work 444,531.91 65,650.94 b. Adjustment Comp. -9,876.28 0.00 3. Materials on Hand 57,510.43 49,996.46 4. Earned Subject to Retention 18,335,108.47 432,930.60 5. Mobilization 2,613,086.00 0.00 6. Total Work Completed 20,890,684.04 7. Deductions -72,809.48 -10,000.00 8. a.Contract Retentions -916,755.42 -21,646.53 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,958,629.57 401,284.07 10. Reduction Amt to Escrow 11. Payment to Escrow 916,750.00 12. Net Pymt. this Estimate 401,284.07