Dept. of Trans. PROGRESS Serial No. Contract No. 03-142-07-52 06-342324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 76% 06-FRE-180-R55.4/R56.6 Federal Project: ACNH-X019(15) HP21-6086(10) L-6086(10) Progress payment No. 20 Payment period ending: 05-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01856 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,150,490.80 1,307,548.39 2.a. Extra Work 468,308.85 23,776.94 b. Adjustment Comp. -9,876.28 0.00 3. Materials on Hand 144,268.43 86,758.00 4. Earned Subject to Retention 19,753,191.80 1,418,083.33 5. Mobilization 2,613,086.00 0.00 6. Total Work Completed 22,222,009.37 7. Deductions -82,809.48 -10,000.00 8. a.Contract Retentions -987,659.59 -70,904.17 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,295,808.73 1,337,179.16 10. Reduction Amt to Escrow 11. Payment to Escrow 987,650.00 12. Net Pymt. this Estimate 1,337,179.16