Dept. of Trans. PROGRESS Serial No. Contract No. 03-169-13-24 06-342324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 82% 06-FRE-180-R55.4/R56.6 Federal Project: ACNH-X019(15) HP21-6086(10) L-6086(10) Progress payment No. 21 Payment period ending: 06-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01856 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,008,836.50 858,345.70 2.a. Extra Work 508,284.41 39,975.56 b. Adjustment Comp. -9,876.28 0.00 3. Materials on Hand 144,268.43 0.00 4. Earned Subject to Retention 20,651,513.06 898,321.26 5. Mobilization 2,613,086.00 0.00 6. Total Work Completed 23,120,330.63 7. Deductions -303,845.91 -221,036.43 8. a.Contract Retentions -1,032,575.65 -44,916.06 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,928,177.50 632,368.77 10. Reduction Amt to Escrow 11. Payment to Escrow 1,032,570.00 12. Net Pymt. this Estimate 632,368.77