Dept. of Trans. PROGRESS Serial No. Contract No. 02-295-14-10 06-342424 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 5% 06-FRE-180-R60.3/R64.0 Federal Project: ACNH-P180(44) Progress payment No. 02 Payment period ending: 10-20-02 E L YEAGER CONSTRUCTION COMPANY INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 693,555.70 628,245.70 2.a. Extra Work 2,269.91 2,269.91 b. Adjustment Comp. 125,000.00 125,000.00 3. Materials on Hand 4. Earned Subject to Retention 820,825.61 755,515.61 5. Mobilization 6. Total Work Completed 820,825.61 7. Deductions 8. a.Contract Retentions -82,082.56 -75,551.56 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 738,743.05 679,964.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 679,964.05