Dept. of Trans. PROGRESS Serial No. Contract No. 08-143-05-10 06-342434 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 14% 06-FRE-180-R63.3/R66.5 Federal Project: NONE Progress payment No. 04 Payment period ending: 05-20-08 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02357 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,419,630.37 4,497,611.85 2.a. Extra Work 14,937.83 10,373.95 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 8,434,568.20 4,507,985.80 5. Mobilization 525,000.00 175,000.00 6. Total Work Completed 8,959,568.20 7. Deductions -30,846.48 -30,846.48 8. a.Contract Retentions -843,456.82 -450,798.58 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,085,264.90 4,201,340.74 10. Reduction Amt to Escrow 11. Payment to Escrow 843,450.00 12. Net Pymt. this Estimate 4,201,340.74