Dept. of Trans. PROGRESS Serial No. Contract No. 08-268-08-13 06-342434 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 35% 06-FRE-180-R63.3/R66.5 Federal Project: NONE Progress payment No. 11 Payment period ending: 09-20-08 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02357 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,259,053.49 1,992,780.70 2.a. Extra Work 163,162.71 2,060.60 b. Adjustment Comp. 63,195.04 0.00 3. Materials on Hand 252,636.79 -24,156.05 4. Earned Subject to Retention 19,738,048.03 1,970,685.25 5. Mobilization 665,000.00 0.00 6. Total Work Completed 20,150,411.24 7. Deductions -16,000.00 18,046.48 8. a.Contract Retentions -986,902.40 -27,334.34 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,400,145.63 1,961,397.39 10. Reduction Amt to Escrow 11. Payment to Escrow 986,900.00 12. Net Pymt. this Estimate 1,961,397.39