Dept. of Trans. PROGRESS Serial No. Contract No. 08-330-08-39 06-342434 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 44% 06-FRE-180-R63.3/R66.5 Federal Project: NONE Progress payment No. 13 Payment period ending: 11-20-08 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02357 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,704,579.71 3,642,424.79 2.a. Extra Work 177,336.90 10,839.44 b. Adjustment Comp. 59,051.29 -4,143.75 3. Materials on Hand 484,523.64 270,184.28 4. Earned Subject to Retention 25,425,491.54 3,919,304.76 5. Mobilization 700,000.00 35,000.00 6. Total Work Completed 25,640,967.90 7. Deductions -106,000.00 -50,000.00 8. a.Contract Retentions -1,271,274.58 -195,965.24 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 24,748,216.96 3,708,339.52 10. Reduction Amt to Escrow 11. Payment to Escrow 1,271,270.00 12. Net Pymt. this Estimate 3,708,339.52