Dept. of Trans. PROGRESS Serial No. Contract No. 09-083-06-19 06-342434 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 63% 06-FRE-180-R63.3/R66.5 Federal Project: NONE Progress payment No. 18 Payment period ending: 03-20-09 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02357 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,191,486.89 2,280,066.59 2.a. Extra Work 250,516.99 21,658.39 b. Adjustment Comp. 59,051.29 0.00 3. Materials on Hand 1,256,272.55 -133,824.59 4. Earned Subject to Retention 34,757,327.72 2,167,900.39 5. Mobilization 700,000.00 0.00 6. Total Work Completed 34,201,055.17 7. Deductions -112,311.69 0.00 8. a.Contract Retentions -1,737,866.39 -108,395.02 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 33,607,149.64 2,059,505.37 10. Reduction Amt to Escrow 11. Payment to Escrow 1,737,860.00 12. Net Pymt. this Estimate 2,059,505.37