Dept. of Trans. PROGRESS Serial No. Contract No. 09-237-05-38 06-342434 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 86% 06-FRE-180-R63.3/R66.5 Federal Project: NONE Progress payment No. 23 Payment period ending: 08-20-09 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02357 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,517,682.70 1,332,444.94 2.a. Extra Work 295,209.14 4,567.50 b. Adjustment Comp. 59,051.29 0.00 3. Materials on Hand 269,003.44 269,003.44 4. Earned Subject to Retention 44,140,946.57 1,606,015.88 5. Mobilization 700,000.00 0.00 6. Total Work Completed 44,571,943.13 7. Deductions -314,791.69 0.00 8. a.Contract Retentions -2,207,047.33 -80,300.80 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 42,319,107.55 1,525,715.08 10. Reduction Amt to Escrow 11. Payment to Escrow 2,207,040.00 12. Net Pymt. this Estimate 1,525,715.08