Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-151-07-10 06-342434 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-FRE-180-R63.3/R66.5 Federal Project: NONE Progress payment No. 41 Payment period ending: 11-05-10 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02357 Total Estimate This Estimate 1. Contract Itms Without Mobil. 47,482,446.80 0.00 2.a. Extra Work 1,114,885.17 61,005.67 b. Adjustment Comp. 76,824.66 0.00 3. Materials on Hand 4. Earned Subject to Retention 48,674,156.63 61,005.67 5. Mobilization 700,000.00 0.00 6. Total Work Completed 49,374,156.63 7. Deductions -234,388.07 10,000.00 8. a.Contract Retentions -2,410,077.75 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,410,077.75 0.00 9. Total pay to Contractor 49,139,768.56 71,005.67 10. Reduction Amt to Escrow -2,410,070.00 0.00 11. Payment to Escrow 2,410,070.00 12. Net Pymt. this Estimate 71,005.67