Dept. of Trans. FINAL Serial No. Contract No. 11-167-05-33 06-342434 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-FRE-180-R63.3/R66.5 Federal Project: NONE Progress payment No. 42 Payment period ending: 11-05-10 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02357 Total Estimate This Estimate 1. Contract Itms Without Mobil. 47,484,446.80 2,000.00 2.a. Extra Work 1,190,438.76 75,553.59 b. Adjustment Comp. -42,771.72 -119,596.38 3. Materials on Hand 4. Earned Subject to Retention 48,632,113.84 -42,042.79 5. Mobilization 700,000.00 0.00 6. Total Work Completed 49,332,113.84 7. Deductions -114,791.69 119,596.38 8. a.Contract Retentions -2,410,077.75 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,410,077.75 0.00 9. Total pay to Contractor 49,217,322.15 77,553.59 10. Reduction Amt to Escrow -2,410,070.00 0.00 11. Payment to Escrow 2,410,070.00 12. Net Pymt. this Estimate 77,553.59