Dept. of Trans. PROGRESS Serial No. Contract No. 18-201-10-53 06-342534 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 46% Location: Federal Project: 06-FRE-180-R74.1/R78.6 ACNH-S180(59) Progress payment No. 014 Payment period ending: 07-20-18 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,633,026.52 3,069,303.48 2. a. Extra Work 137,080.65 750.00 b. Adustment Comp. 860,982.00 0.00 3. Materials on Hand 139,246.20 0.00 4. Earned Subject to Retention 16,770,335.37 3,070,053.48 5. Mobilization 2,802,500.00 0.00 6. Total Work Completed 19,433,589.17 7. Deductions -20,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,552,835.37 3,065,053.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,065,053.48