Dept. of Trans. PROGRESS Serial No. Contract No. 19-143-09-17 06-342534 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 55% Location: Federal Project: 06-FRE-180-R74.1/R78.6 ACNH-S180(59) Progress payment No. 024 Payment period ending: 05-20-19 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,305,146.51 1,484,498.59 2. a. Extra Work 197,951.40 14,915.81 b. Adustment Comp. 925,971.76 64,989.76 3. Materials on Hand 87,550.00 0.00 4. Earned Subject to Retention 28,516,619.67 1,564,404.16 5. Mobilization 2,950,000.00 0.00 6. Total Work Completed 31,379,069.67 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,466,619.67 1,564,404.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,564,404.16