Dept. of Trans. PROGRESS Serial No. Contract No. 19-261-14-05 06-342534 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 65% Location: Federal Project: 06-FRE-180-R74.1/R78.6 ACNH-S180(59) Progress payment No. 028 Payment period ending: 09-20-19 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,743,170.00 2,367,813.34 2. a. Extra Work 273,398.09 40,691.47 b. Adustment Comp. 925,971.76 0.00 3. Materials on Hand 87,550.00 0.00 4. Earned Subject to Retention 35,030,089.85 2,408,504.81 5. Mobilization 2,950,000.00 0.00 6. Total Work Completed 37,892,539.85 7. Deductions -65,175.00 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 37,914,914.85 2,378,504.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,378,504.81