Dept. of Trans. PROGRESS Serial No. Contract No. 20-021-15-02 06-342534 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 77% Location: Federal Project: 06-FRE-180-R74.1/R78.6 ACNH-S180(59) Progress payment No. 032 Payment period ending: 01-20-20 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,204,337.26 1,127,824.48 2. a. Extra Work 342,459.72 11,257.95 b. Adustment Comp. 965,625.22 3,826.44 3. Materials on Hand 10,164.78 -4,676.23 4. Earned Subject to Retention 40,522,586.98 1,138,232.64 5. Mobilization 2,950,000.00 0.00 6. Total Work Completed 43,462,422.20 7. Deductions -85,175.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 43,387,411.98 1,118,232.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,118,232.64