Dept. of Trans. SEMI-FINAL Serial No. Contract No. 21-013-11-09 06-342534 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-FRE-180-R74.1/R78.6 ACNH-S180(59) Progress payment No. 044 Payment period ending: 12-04-20 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 48,560,745.26 -10,006.40 2. a. Extra Work 864,083.87 40,552.63 b. Adustment Comp. 1,044,563.50 -28,109.12 3. Materials on Hand 4. Earned Subject to Retention 50,469,392.63 2,437.11 5. Mobilization 2,950,000.00 0.00 6. Total Work Completed 53,419,392.63 7. Deductions -147,170.75 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 53,272,221.88 2,437.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,437.11