Dept. of Trans. PROGRESS Serial No. Contract No. 06-081-07-55 06-350704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 1% 12% 06-FRE-99-R0.7/7.4 Federal Project: ACNH-P099(450) ACBH-P099(450) NH-P099(450) Progress payment No. 02 Payment period ending: 03-20-06 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 665,646.24 626,646.24 2.a. Extra Work 4,683.00 0.00 b. Adjustment Comp. 3. Materials on Hand 62,646.50 62,646.50 4. Earned Subject to Retention 732,975.74 689,292.74 5. Mobilization 6. Total Work Completed 670,329.24 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 732,975.74 689,292.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 689,292.74