Dept. of Trans. PROGRESS Serial No. Contract No. 06-234-06-29 06-350704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 35% 06-FRE-99-R0.7/7.4 Federal Project: ACNH-P099(450) ACBH-P099(450) NH-P099(450) Progress payment No. 07 Payment period ending: 08-20-06 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,573,973.18 1,918,345.50 2.a. Extra Work 121,824.01 6,675.40 b. Adjustment Comp. 5,401.36 1,527.14 3. Materials on Hand 478,014.56 356,789.58 4. Earned Subject to Retention 9,179,213.11 2,283,337.62 5. Mobilization 4,251,000.00 0.00 6. Total Work Completed 12,952,198.55 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,420,213.11 2,283,337.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,283,337.62