Dept. of Trans. PROGRESS Serial No. Contract No. 07-023-15-23 06-350704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 43% 51% 06-FRE-99-R0.7/7.4 Federal Project: ACNH-P099(450) ACBH-P099(450) NH-P099(450) Progress payment No. 12 Payment period ending: 01-20-07 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,462,449.03 1,018,938.22 2.a. Extra Work 224,142.80 -1,700.74 b. Adjustment Comp. 5,401.36 0.00 3. Materials on Hand 0.00 -20,752.80 4. Earned Subject to Retention 19,691,993.19 996,484.68 5. Mobilization 5,384,600.00 0.00 6. Total Work Completed 25,076,593.19 7. Deductions -146,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 24,930,593.19 996,484.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 996,484.68