Dept. of Trans. PROGRESS Serial No. Contract No. 07-234-06-26 06-350704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 100% 06-FRE-99-R0.7/7.4 Federal Project: ACNH-P099(450) ACBH-P099(450) NH-P099(450) Progress payment No. 21 Payment period ending: 08-20-07 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,222,897.51 2,820,102.33 2.a. Extra Work 944,787.26 379,418.74 b. Adjustment Comp. 273,381.36 0.00 3. Materials on Hand 993,052.22 72,923.82 4. Earned Subject to Retention 45,434,118.35 3,272,444.89 5. Mobilization 5,668,000.00 0.00 6. Total Work Completed 50,109,066.13 7. Deductions -896,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 85,206.55 c. Reduction after 95% Comp. 9. Total pay to Contractor 50,206,118.35 3,347,651.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,347,651.44