Dept. of Trans. PROGRESS Serial No. Contract No. 08-023-07-57 06-350704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 06-FRE-99-R0.7/7.4 Federal Project: ACNH-P099(450) ACBH-P099(450) NH-P099(450) Progress payment No. 28 Payment period ending: 01-20-08 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 51,400,306.96 49,749.30 2.a. Extra Work 1,959,610.55 197,346.96 b. Adjustment Comp. 328,473.78 34,750.00 3. Materials on Hand 4. Earned Subject to Retention 53,688,391.29 281,846.26 5. Mobilization 5,668,000.00 0.00 6. Total Work Completed 59,356,391.29 7. Deductions -40,974.93 -4,974.93 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 59,315,416.36 276,871.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 276,871.33