Dept. of Trans. PROGRESS Serial No. Contract No. 00-327-07-04 06-353904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 67% 06-KER-65-8.1/8.5 Federal Project: ACNH-P065(61) Progress payment No. 06 Payment period ending: 11-20-00 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01484 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,160,285.70 215,358.50 2.a. Extra Work 38,593.95 -25.89 b. Adjustment Comp. 3,920.62 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,202,800.27 215,332.61 5. Mobilization 160,080.00 0.00 6. Total Work Completed 1,362,880.27 7. Deductions 8. a.Contract Retentions -60,140.01 -10,766.63 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,302,740.26 204,565.98 10. Reduction Amt to Escrow 11. Payment to Escrow 60,140.00 12. Net Pymt. this Estimate 204,565.98