Dept. of Trans. PROGRESS Serial No. Contract No. 11-144-09-35 06-3568U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 47% 06-KIN-198-R21.5/R28.3 Federal Project: 06-TUL-198-0.0/R3.4 HPLU-6206(15) Progress payment No. 21 Payment period ending: 05-20-11 FLATIRON WEST INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,512,442.34 358,285.22 2.a. Extra Work 586,048.15 7,499.21 b. Adjustment Comp. 401,230.82 0.00 3. Materials on Hand 760,915.38 0.00 4. Earned Subject to Retention 25,260,636.69 365,784.43 5. Mobilization 4,510,000.00 0.00 6. Total Work Completed 29,009,721.31 7. Deductions -78,269.00 76,148.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 29,692,367.69 441,932.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 441,932.43