Dept. of Trans. PROGRESS Serial No. Contract No. 11-265-10-35 06-3568U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 63% 06-KIN-198-R21.5/R28.3 Federal Project: 06-TUL-198-0.0/R3.4 HPLU-6206(15) Progress payment No. 25 Payment period ending: 09-20-11 FLATIRON WEST INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,356,945.69 990,152.68 2.a. Extra Work 937,891.55 69,834.60 b. Adjustment Comp. 509,604.54 860.53 3. Materials on Hand 720,292.34 -20,263.50 4. Earned Subject to Retention 28,524,734.12 1,040,584.31 5. Mobilization 4,510,000.00 0.00 6. Total Work Completed 32,314,441.78 7. Deductions -92,269.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,942,465.12 1,040,584.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,040,584.31