Dept. of Trans. PROGRESS Serial No. Contract No. 15-022-09-08 06-360214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 80% 06-TUL-99-37.3/41.3 Federal Project: NONE Progress payment No. 22 Payment period ending: 01-20-15 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,274,900.79 180,416.09 2.a. Extra Work 520,998.42 164,046.05 b. Adjustment Comp. 3. Materials on Hand 120,946.34 0.00 4. Earned Subject to Retention 17,916,845.55 344,462.14 5. Mobilization 1,586,379.11 0.00 6. Total Work Completed 19,382,278.32 7. Deductions -19,161.43 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,484,063.23 344,462.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 344,462.14