Dept. of Trans. PROGRESS Serial No. Contract No. 15-146-14-20 06-360214 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 89% Location: Federal Project: 06-TUL-99-37.3/41.3 NONE Progress payment No. 026 Payment period ending: 05-20-15 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,426,748.67 537,729.02 2. a. Extra Work 641,051.12 66,789.94 b. Adustment Comp. 3. Materials on Hand 41,377.34 -79,569.00 4. Earned Subject to Retention 20,109,177.13 524,949.96 5. Mobilization 1,586,379.11 0.00 6. Total Work Completed 21,654,178.90 7. Deductions -19,161.43 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,676,394.81 524,949.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 524,949.96