Dept. of Trans. PROGRESS Serial No. Contract No. 16-053-10-16 06-360214 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 98% Location: Federal Project: 06-TUL-99-37.3/41.3 NONE Progress payment No. 036 Payment period ending: 02-20-16 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,147,294.48 470,432.35 2. a. Extra Work 963,920.82 3,519.71 b. Adustment Comp. 225,878.07 305,237.62 3. Materials on Hand 4. Earned Subject to Retention 31,337,093.37 779,189.68 5. Mobilization 1,586,379.11 0.00 6. Total Work Completed 32,923,472.48 7. Deductions -469,161.43 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,454,311.05 789,189.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 789,189.68