Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-318-09-26 06-360214 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-TUL-99-37.3/41.3 NONE Progress payment No. 048 Payment period ending: 06-24-16 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,625,526.95 0.00 2. a. Extra Work 2,655,841.22 0.00 b. Adustment Comp. 563,488.10 94,009.04 3. Materials on Hand 4. Earned Subject to Retention 34,844,856.27 94,009.04 5. Mobilization 1,586,379.11 0.00 6. Total Work Completed 36,431,235.38 7. Deductions -19,161.43 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 36,412,073.95 94,009.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 94,009.04