Dept. of Trans. PROGRESS Serial No. Contract No. 05-024-09-01 06-361404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 30% 06-TUL-245-16.0/16.7 Federal Project: ACST-P245(26) P-P245(26) ACBR-P245(26) Progress payment No. 02 Payment period ending: 01-20-05 AGEE CONSTRUCTION CORPORATION P O BOX 629 CLOVIS CA 93613 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 166,651.95 97,455.60 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 166,651.95 97,455.60 5. Mobilization 82,500.00 27,500.00 6. Total Work Completed 249,151.95 7. Deductions -40,927.99 -23,628.90 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 208,223.96 101,326.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 101,326.70