Dept. of Trans. PROGRESS Serial No. Contract No. 05-297-07-08 06-361404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 06-TUL-245-16.0/16.7 Federal Project: ACST-P245(26) P-P245(26) ACBR-P245(26) Progress payment No. 11 Payment period ending: 10-20-05 AGEE CONSTRUCTION CORPORATION P O BOX 629 CLOVIS CA 93613 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 950,968.62 1,398.00 2.a. Extra Work 18,001.59 2,874.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 968,970.21 4,272.00 5. Mobilization 110,000.00 0.00 6. Total Work Completed 1,078,970.21 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,078,970.21 4,272.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,272.00