Dept. of Trans. PROGRESS Serial No. Contract No. 00-298-08-15 06-389504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 66% 06-KER-58-R101.5/R107.7 Federal Project: ACNH-P058(80) Progress payment No. 08 Payment period ending: 10-20-00 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01411 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,183,323.08 1,838,351.44 2.a. Extra Work 133,050.16 4,597.37 b. Adjustment Comp. 52,361.39 -19,371.03 3. Materials on Hand 4. Earned Subject to Retention 6,368,734.63 1,823,577.78 5. Mobilization 6. Total Work Completed 6,368,734.63 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -318,436.73 -91,178.89 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,040,297.90 1,732,398.89 10. Reduction Amt to Escrow 11. Payment to Escrow 220,000.00 12. Net Pymt. this Estimate 1,732,398.89