Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-184-05-44 06-3937U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-TUL-137-15.0/15.9 Federal Project: NONE Progress payment No. 08 Payment period ending: 06-20-07 LEES PAVING INC 1212 N PLAZA DRIVE VISALIA CA 93291 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 882,943.95 0.00 2.a. Extra Work 45,681.75 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 928,625.70 0.00 5. Mobilization 35,000.00 0.00 6. Total Work Completed 963,625.70 7. Deductions -35,000.00 -20,000.00 8. a.Contract Retentions -46,431.29 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 46,431.29 46,431.29 9. Total pay to Contractor 928,625.70 26,431.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,431.29