Dept. of Trans. PROGRESS Serial No. Contract No. 19-295-09-49 06-394604 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 81% Location: Federal Project: 06-FRE-269-10.6/12.4 ACST-P269(13) Progress payment No. 009 Payment period ending: 10-20-19 TEICHERT CONSTRUCTION PO BOX 13557 SACRAMENTO CA 95853 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,840,835.83 1,400,359.41 2. a. Extra Work 121,754.72 47,726.17 b. Adustment Comp. 554,035.83 10,866.14 3. Materials on Hand 4. Earned Subject to Retention 12,516,626.38 1,458,951.72 5. Mobilization 1,400,000.00 0.00 6. Total Work Completed 13,916,626.38 7. Deductions -20,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,896,626.38 1,448,951.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,448,951.72