Dept. of Trans. PROGRESS Serial No. Contract No. 03-295-06-35 06-402904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 100% 06-MAD-145-R0.0/ .0 Federal Project: ACST-P145(22) P-P145(22) ACBR-P145(22) Progress payment No. 17 Payment period ending: 10-20-03 W JAXON BAKER INC AND SHASTA CONSTRUCTORS INC A JOINT VENTURE P O BOX 994248 REDDING CA 960994248 Escrow No. 01967 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,353,574.70 388,402.24 2.a. Extra Work 46,614.97 426.54 b. Adjustment Comp. 43,629.58 0.00 3. Materials on Hand 34,503.20 0.00 4. Earned Subject to Retention 3,478,322.45 388,828.78 5. Mobilization 512,000.00 0.00 6. Total Work Completed 3,955,819.25 7. Deductions 8. a.Contract Retentions -173,916.12 -19,441.44 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,816,406.33 369,387.34 10. Reduction Amt to Escrow 11. Payment to Escrow 173,910.00 12. Net Pymt. this Estimate 369,387.34