Dept. of Trans. PROGRESS Serial No. Contract No. 02-142-07-06 06-403504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 4% 06-TUL-198-R8.8/R11.9 Federal Project: NH-P198(38) Progress payment No. 03 Payment period ending: 05-20-02 WATKIN AND BORTOLUSSI INC 77 LARKSPUR STREET SAN RAFAEL CA 949014886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 98,183.00 23,090.00 2.a. Extra Work 53,205.74 53,205.74 b. Adjustment Comp. 3. Materials on Hand 50,462.71 50,462.71 4. Earned Subject to Retention 201,851.45 126,758.45 5. Mobilization 105,750.00 35,250.00 6. Total Work Completed 257,138.74 7. Deductions 8. a.Contract Retentions -20,185.15 -12,675.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 287,416.30 149,332.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 149,332.60