Dept. of Trans. PROGRESS Serial No. Contract No. 02-204-08-16 06-403504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 9% 06-TUL-198-R8.8/R11.9 Federal Project: NH-P198(38) Progress payment No. 05 Payment period ending: 07-20-02 WATKIN AND BORTOLUSSI INC 77 LARKSPUR STREET SAN RAFAEL CA 949014886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 395,011.19 119,418.00 2.a. Extra Work 61,631.41 0.00 b. Adjustment Comp. 3. Materials on Hand 47,390.71 -10,545.13 4. Earned Subject to Retention 504,033.31 108,872.87 5. Mobilization 133,950.00 0.00 6. Total Work Completed 590,592.60 7. Deductions 8. a.Contract Retentions -27,045.00 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 610,938.31 108,872.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 108,872.87