Dept. of Trans. PROGRESS Serial No. Contract No. 03-357-05-47 06-404104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 15% 7% 06-FRE-99-19.8/24.2 Federal Project: ACNH-P099(418) Progress payment No. 05 Payment period ending: 12-20-03 WATKIN AND BORTOLUSSI INC 77 LARKSPUR STREET SAN RAFAEL CA 94901 Escrow No. 01764 Total Estimate This Estimate 1. Contract Itms Without Mobil. 80,170.00 60,880.00 2.a. Extra Work 23,080.05 0.00 b. Adjustment Comp. 3. Materials on Hand 10,681.74 10,681.74 4. Earned Subject to Retention 113,931.79 71,561.74 5. Mobilization 80,250.00 80,250.00 6. Total Work Completed 183,500.05 7. Deductions -1,000.00 0.00 8. a.Contract Retentions -11,393.18 -7,156.17 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 181,788.61 144,655.57 10. Reduction Amt to Escrow 11. Payment to Escrow 11,390.00 12. Net Pymt. this Estimate 144,655.57