Dept. of Trans. PROGRESS Serial No. Contract No. 04-113-08-01 06-404104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 15% 06-FRE-99-19.8/24.2 Federal Project: ACNH-P099(418) Progress payment No. 09 Payment period ending: 04-20-04 WATKIN AND BORTOLUSSI INC 77 LARKSPUR STREET SAN RAFAEL CA 94901 Escrow No. 01764 Total Estimate This Estimate 1. Contract Itms Without Mobil. 576,031.00 145,479.00 2.a. Extra Work 84,727.49 16,200.12 b. Adjustment Comp. 3. Materials on Hand 44,895.18 44,895.18 4. Earned Subject to Retention 705,653.67 206,574.30 5. Mobilization 107,000.00 5,350.00 6. Total Work Completed 767,758.49 7. Deductions 8. a.Contract Retentions -35,282.68 -10,328.71 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 777,370.99 201,595.59 10. Reduction Amt to Escrow 11. Payment to Escrow 35,280.00 12. Net Pymt. this Estimate 201,595.59