Dept. of Trans. SEMI-FINAL Serial No. Contract No. 03-036-14-04 06-407704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-202-8.9/12.1 Federal Project: ACST-S202(4) P-S202(4) Progress payment No. 20 Payment period ending: 12-31-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01816 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,605,882.17 24,529.80 2.a. Extra Work 440,284.93 14,486.50 b. Adjustment Comp. 16,328.16 -9,190.84 3. Materials on Hand 4. Earned Subject to Retention 6,062,495.26 29,825.46 5. Mobilization 620,000.00 0.00 6. Total Work Completed 6,682,495.26 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -300,185.36 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 300,185.36 0.00 9. Total pay to Contractor 6,672,495.26 29,825.46 10. Reduction Amt to Escrow -200,000.00 0.00 11. Payment to Escrow 200,000.00 12. Net Pymt. this Estimate 29,825.46